The concrete footings are complete and ready for the placement of the new Goldcorp Express towers. Most all of parts of the new lift have arrived and are ready for installation. In the meantime, the work at the top of the mountain continues.
The next big event will be flying the towers to the new locations. The plan is to complete that job in mid July. Once a specific date is scheduled we will post the information right here.